Short answer: FDOT lists a $63.3 million construction cost for repaving a 24.1-mile stretch of I-95 that runs through Melbourne, and $10.1 million for resurfacing and safety work on 2.1 miles of U.S. 1 between Myers Drive and Crane Creek Bridge, where FDOT says new medians will restrict some left turns. FDOT is also studying U.S. 1 shoreline erosion, the city began a Norfolk Parkway corridor study in July 2025, and its 2025 Year in Review reports 12.5 centerline miles resurfaced.
Last verified: October 22, 2026, against the sources listed at the end of this page.
Which road projects are under way or under study in Melbourne?
FDOT has resurfacing jobs under construction on I-95 and U.S. 1 in Melbourne and a shoreline study on U.S. 1, while the City of Melbourne is running the Norfolk Parkway corridor study and Southwest Trails.
The state work sits on CFLRoads, the Florida Department of Transportation's Central Florida project site, where each Melbourne job has its own page with scope, cost, contacts and a comment form (CFLRoads, I-95 448977-1; CFLRoads, U.S. 1 448793-1). FDOT also lists a planning study of the U.S. 1 shoreline beside the Indian River in Melbourne and Palm Bay (CFLRoads, 456175-1). City projects are posted by the Melbourne Engineering Department (City of Melbourne, Norfolk Parkway).
| Project | Agency | Limits | Phase and cost in the record | Source |
|---|---|---|---|---|
| I-95 resurfacing, 448977-1 | FDOT | South of Malabar Road to north of Fiske Boulevard, 24.1 miles | Construction; project start listed as early 2025; construction cost $63.3 million | CFLRoads 448977-1 |
| U.S. 1 (S.R. 5) resurfacing and safety work, 448793-1 | FDOT | Myers Drive to Crane Creek Bridge, 2.1 miles | Construction; project start listed as fall 2025; construction cost $10.1 million | CFLRoads 448793-1 |
| U.S. 1 shoreline stabilization study, 456175-1 | FDOT | Carolin Street to Laurie Street, 1.9 miles, in Melbourne | Planning; builds on a feasibility study completed in 2022; no cost listed | CFLRoads 456175-1 |
| Norfolk Parkway Extension ACE study | City of Melbourne with FDOT | Minton Road to St. Johns Heritage Parkway | Study began July 2025; corridor development initiated October 2025 | City of Melbourne |
| Southwest Trails | City of Melbourne | Dairy Road, Florida Avenue, University Boulevard and a drainage canal | Construction reported underway in the 2025 Year in Review | 2025 Year in Review |
The Ellis Road widening near Melbourne Orlando International Airport has its own Digital Towns guide under West Melbourne, and road ownership and where to report a pothole or signal problem are covered in the Melbourne transportation guide.
What is FDOT doing on I-95 through Melbourne?
Under project 448977-1, FDOT is repaving both directions of I-95 for 24.1 miles, from south of Malabar Road to north of Fiske Boulevard, in Melbourne and Palm Bay, with a listed construction cost of $63.3 million.
The project page lists the ramps being repaved at Malabar Road, Palm Bay Road (C.R. 516), U.S. 192, Eau Gallie Boulevard (S.R. 518), the Pineda Causeway (S.R. 404), Wickham Road and Fiske Boulevard (CFLRoads 448977-1). It also adds barriers to protect overpass piers at Minton Road, S.R. 404 and Viera Boulevard, puts new deck coatings on the bridges over Eau Gallie Boulevard and Lake Washington Road, upgrades pavement markings and improves the Intelligent Transportation System. FDOT lists the work type as resurfacing, the phase as construction and the project start as early 2025.
The I-95 page posts a project flyer dated March 31, 2026, a lane closures section for the paving work and a last updated date of October 16, 2026 (CFLRoads 448977-1). Closures on the Melbourne stretch change week to week, so the page and the CFLRoads lane closures listing for Brevard are where drivers find the current ones.
What is changing on U.S. 1 between Myers Drive and Crane Creek?
FDOT project 448793-1 resurfaces 2.1 miles of U.S. 1 between Myers Drive and Crane Creek Bridge in Melbourne and Palm Bay and adds buffered bike lanes, rebuilt curb ramps, enhanced lighting and elements of a city Streetscape project, at a construction cost of $10.1 million.
According to the project page, the work covers resurfacing, drainage improvements, sidewalk enhancements and safety upgrades on U.S. 1 (S.R. 5) (CFLRoads 448793-1). Travel lanes are being restriped to make room for 7-foot-wide buffered bicycle lanes from Myers Drive to University Boulevard, pedestrian curb ramps are being rebuilt to current ADA standards, pedestrian signals are to be upgraded and lighting is enhanced at signalized intersections. FDOT lists the start as fall 2025.
The City of Melbourne Streetscape elements in the FDOT job include raised medians from Avenida Del Rio to Crane Creek Bridge and directional medians at Roosevelt Avenue and Jernigan Avenue (CFLRoads 448793-1). FDOT says those medians will restrict left turns from some side streets and driveways onto U.S. 1. The page keeps the October 3, 2023 public meeting exhibit and presentation and a project flyer dated September 18, 2026. FDOT names CWR Contracting, Inc. as contractor on the I-95 job and Timothy Rose Contracting Inc. on U.S. 1 (CFLRoads 448977-1). Both pages list the FDOT communications team line, (321) 634-6111.
Why is FDOT studying the U.S. 1 shoreline in Melbourne?
FDOT is evaluating long-term shoreline stabilization along U.S. 1 beside the Indian River, including a 1.9-mile Melbourne segment from Carolin Street to Laurie Street, where it wants to prevent further erosion and slope failures.
Project 456175-1 is a corridor planning study covering two segments in Brevard County: Carolin Street to Laurie Street in the City of Melbourne, and Hiawatha Avenue to Kingswood Drive, 0.9 miles, in the City of Palm Bay (CFLRoads 456175-1). Building on a feasibility study completed in 2022, FDOT says it will weigh engineering alternatives to prevent further erosion from wave action at the base of the slope and to repair and reestablish the slopes against future failures.
The study page, which names Melbourne and Palm Bay as the cities covered, lists the work type as corridor planning and the phase as planning, shows no construction cost, says project documents and meeting announcements will be uploaded as they become available, and shows a last updated date of August 24, 2026 (CFLRoads 456175-1). A comment form on the same page reaches the FDOT planning project manager's office.
Where does the Norfolk Parkway extension study stand?
The City of Melbourne and FDOT began the Norfolk Parkway Extension Alternative Corridor Evaluation in July 2025 and started developing candidate corridors in October 2025, for a new road between Minton Road, the eastern limit, and St. Johns Heritage Parkway, the western limit.
The Melbourne Engineering page defines an ACE study as an early planning step that identifies, evaluates and documents workable corridor alternatives, screening fatal flaws, environmental constraints, mobility needs and multimodal connectivity to decide which alignments advance to the Project Development and Environment phase (City of Melbourne, Norfolk Parkway ACE study). The study considers new alignment corridors of about 200 feet in width. Data collection ran from July to August 2025 and included the traffic forecast and a land suitability analysis.
Federal environmental review for the project is being carried out by FDOT under 23 U.S.C. 327 and a memorandum of understanding between FHWA and FDOT dated May 26, 2022, the city page notes, and public meetings will be announced there (City of Melbourne). The Space Coast TPO's partner project list shows a separate ACE study for the Palm Bay Parkway section of St. Johns Heritage Parkway, evaluating new corridors between Babcock Street and Malabar Road, a distance of about 14 miles (Space Coast TPO partner projects).
What road and sidewalk work did Melbourne finish in 2025?
Melbourne's 2025 Year in Review reports 12.5 centerline miles of city roads resurfaced, a rebuilt Bignonia Street culvert, a new Nicklaus Drive storm pipe and new sidewalks near Stone Magnet Middle School and on NASA Boulevard.
The resurfacing followed the city's Pavement Management Plan (Melbourne 2025 Year in Review). A failing culvert under Bignonia Street, which drains a substantial part of downtown Melbourne, was removed and replaced and the roadway reconstructed with help from American Rescue Plan Act funding. Under Nicklaus Drive, two failing 36-inch metal stormwater pipes were replaced with a single 84-inch reinforced concrete pipe.
Around Stone Magnet Middle School the city added 1.2 miles of sidewalk on Lipscomb Street, Monroe Street and University Boulevard, with Rectangular Rapid Flashing Beacons and traffic cushions on Monroe and Lipscomb Streets, paid for with federal Safe Routes to School dollars through FDOT (Year in Review). Melbourne also finished one mile of sidewalks on NASA Boulevard between Eddie Allen Road and Gateway Drive and a midblock crosswalk upgrade at University Boulevard and Bruce D. Buggs Street, and reported Southwest Trails construction underway.
The Year in Review describes Southwest Trails as nearly two miles of new or upgraded sidewalks and multi-use paths along parts of Dairy Road, Florida Avenue and University Boulevard (Year in Review). The city's Southwest Trails page itemizes the scope as a 10-foot trail of 0.5 miles beside a drainage canal from Florida Avenue to University Boulevard plus 1.34 miles of 6-foot and 8-foot sidewalk, with drainage work at Leonard Weaver Boulevard and University Boulevard (City of Melbourne, Southwest Trails).
Last verified: October 21, 2026, with the three CFLRoads project pages (448977-1, 448793-1, 456175-1), the city Engineering pages on the Norfolk Parkway study and Southwest Trails, Melbourne's 2025 Year in Review and the Space Coast TPO partner project list each checked again that day.
Frequently asked questions
Is I-95 being repaved through Melbourne?
Yes. FDOT project 448977-1 covers 24.1 miles of I-95 from south of Malabar Road to north of Fiske Boulevard, with a listed construction cost of $63.3 million and ramp repaving at interchanges including Wickham Road and Eau Gallie Boulevard.
Will left turns onto U.S. 1 in Melbourne change?
FDOT says raised medians from Avenida Del Rio to the Crane Creek Bridge and directional medians at Roosevelt Avenue and Jernigan Avenue will restrict left turns from some side streets and driveways onto U.S. 1.
What is the Norfolk Parkway extension?
It is a proposed new road from Minton Road to St. Johns Heritage Parkway. The City of Melbourne and FDOT began an Alternative Corridor Evaluation study in July 2025 to compare corridors about 200 feet wide.
What is the U.S. 1 shoreline stabilization study?
FDOT project 456175-1 is a corridor planning study of two U.S. 1 segments beside the Indian River, including Carolin Street to Laurie Street in Melbourne. Building on a 2022 feasibility study, FDOT is evaluating ways to prevent further erosion at the base of the slope and to repair the slopes.
How many miles of Melbourne roads were resurfaced in 2025?
The City of Melbourne's 2025 Year in Review reports 12.5 centerline miles resurfaced under its Pavement Management Plan.
Sources
- 448977-1 I-95 from south of Malabar Road to north of Fiske Boulevard, CFLRoads (FDOT) https://www.cflroads.com/project/448977-1 Used for: scope, length, interchanges, bridge and barrier work, cost, start, contractor, flyer date
- 448793-1 U.S. 1 (S.R. 5) from Myers Drive to Crane Creek Bridge, CFLRoads (FDOT) https://www.cflroads.com/project/448793-1 Used for: scope, bike lanes, city Streetscape medians, cost, start, contractor, public meeting date
- 456175-1 U.S. 1 Shoreline Stabilization Study, CFLRoads (FDOT) https://www.cflroads.com/project/456175-1 Used for: study segments, 2022 feasibility study, purpose, planning phase
- Norfolk Parkway Extension Alternative Corridor Evaluation Study, City of Melbourne https://www.melbourneflorida.org/Government/Departments/Engineering/Norfolk-Parkway-Extension-Alternative-Corridor-Evaluation-Study Used for: ACE definition, limits, corridor width, 2025 milestones, PD&E next phase, 2022 FHWA/FDOT MOU
- Southwest Trails, City of Melbourne Engineering https://www.melbourneflorida.org/Government/Departments/Engineering/Southwest-Trails Used for: scope of work, sidewalk and trail segments, beacons, transit pads, start statement
- Melbourne 2025 Year in Review (PDF), City of Melbourne https://www.melbourneflorida.org/files/assets/public/v/2/melbourne-2025-year-in-review.pdf Used for: 2025 resurfacing miles, Bignonia Street culvert, Nicklaus Drive pipe, Stone Magnet Middle sidewalks, NASA Boulevard sidewalks, Southwest Trails underway
- Ellis Road Widening, Brevard County Public Works https://www.brevardfl.gov/PublicWorks/Projects/EllisRoadWidening Used for: Ellis Road description, 2020 interchange, commuter and traveler estimates, FDOT numbers, clearing and grubbing, spring 2026 schedule statement
- Partner Projects, Space Coast Transportation Planning Organization https://www.spacecoasttpo.com/what-we-do/projects/partner-projects Used for: Ellis Road status and unfunded construction phase; St. Johns Heritage Parkway Palm Bay Parkway section ACE
Published by Rytas Dirse, Solo Founder & AI Architect
Built with AI, held to quality gates. US sources, US brands, facts only.
How this page was made
Digital Towns uses AI assistance to research and write its guides, and every page is only as good as the sources it cites. Our goal is the most accurate, useful local information possible.
If you see an error, or anything you can show is false, tell us right away and we will take a third look.
Report an error
Thank you. We'll take a third look and correct the page if it's wrong.